Two FRP domes for the Islamic Arts Museum Malaysia

Completed
November 2023
Location
Kuala Lumpur
Our role
Design & Build
For
Islamic Arts Museum Malaysia
The FRP dome on the museum roof, September 2023.
The FRP dome on the museum roof, September 2023.
The existing tiled dome before work began, September 2022.
The existing tiled dome before work began, September 2022.
Carving the master pattern in the workshop, November 2022.
Carving the master pattern in the workshop, November 2022.
Steel frames in our workshop, January 2023.
Steel frames in our workshop, January 2023.

Two fibreglass domes for a national museum, one cast in ten segments over the old dome, one cast whole.

The brief

Two fibreglass reinforced polymer domes for the museum, under a Design & Build contract with the museum itself. The main dome was to be finished in cast FRP over its existing structure, matching the original tilework; a second, smaller dome was to be cast whole and installed on a new steel frame.

What we delivered

For the main dome: a galvanised steel frame; a calligraphy band of 22 cast panels carrying Surah An-Nur, verse 35; 64 muqarnas; and the top dome in ten cast segments, 12.6 m in diameter. Each element followed the same route: master pattern and mould, casting, primer and base coat, finish coat, installation, touch-up and clear coat. The second dome was cast as a single FRP shell on its own steel frame.

Our package: the two domes, from design to handover.

Delivery

  1. Nov 2022Master pattern carved
  2. Feb 2023Segments cast and trial-assembled
  3. Aug 2023Segments painted in the workshop
  4. Sep 2023Dome complete on the roof
  5. Nov 2023Handed over

The detail that mattered

The new work had to read as one with the museum’s original glazed tilework. We matched an eleven-colour paint schedule to the old tiles, from the turquoise ground to the gold, green and deep red of the flowers, and finished every piece under clear coat.

The setting-out

Where the dome started.

Before anything was carved, the dome was set out as a drawing: the circle, the radial lines and the border that every segment had to meet.

The setting-out drawing for the main dome: a circle, radial lines and a dotted border.

The site diary

A year of work, month by month.

The old dome being broken out on the museum roof.
Working the ornament into a pattern panel by hand.
The master pattern built up in curved timber strips.
A shell worked by hand in the workshop.
The painted surface, close up.

September 2022

  1. Master pattern carved
  2. Segments cast and trial-assembled
  3. Segments painted in the workshop
  4. Dome complete on the roof
  5. Handed over

September 2022

October 2022

November 2022

December 2022

January 2023

February 2023

March 2023

May 2023

June 2023

August 2023

September 2023

One year apart

The same dome, September to September.

The old tiled dome, September 2022.
September 2022
The new FRP dome on the museum roof, September 2023.
September 2023